NCSC Milestones
A journey of community, culture, and devotion — key moments that shaped the Nepali Cultural & Spiritual Center.
2018
Foundation & Planning
- Steering Committee formed to guide long‑term temple planning.
- Committees for Planning, Engineering, Fundraising, Construction, and Publicity established.
2019
Fundraising & Property Acquisition
- Major fundraising events successfully raised commitments from Patrons, Trustees, and Founding Members.
- Architectural contract signed with Artec Integrated Solutions.
- Dec 18, 2019: Loan closed and 1212 Royal Pkwy, Euless property officially purchased.
2020
Approvals & Design
- Zoning change approved unanimously by the City of Euless & City Council.
- First Phase 1 floor plans shared with the community.
- City approved Phase 1 building permit on August 25, 2020.
- Request for Proposal (RFP) announced for general contractor selection.
2021
Construction Launch
- Formal contract signed with General Contractor Raul Sandoval.
- Apr 15, 2021: Building permit officially issued by the City of Euless.
- Apr 24, 2021: Construction kickoff and puja ceremony with 250+ attendees; $68,000 raised.
2022
Phase 1 Progress & Financing
- Revised grading plan approved by the City of Euless.
- BOT approved bank loan up to $1 million and temporary loans from Patrons/Trustees.
- Project manager hired and oversight committees formed/expanded.
2023
Spiritual Milestone
- Mar 3, 2023: The Gajur (temple pinnacle) installed, symbolizing the spiritual completion of the temple's top structure.
From early planning and fundraising to construction and spiritual milestones, these moments reflect a dedicated journey shaped by devotion, unity, and community effort.